Metro Rail Project Sees 63.2pc Progress: Quader

Road Transport and Bridges Minister Obaidul Quader on Tuesday said the average progress of the construction work of the first metro rail in Bangladesh is 63.2 percent.

He made the remarks while talking to reports after visiting the first metro rail set and the progress of the project work at the Uttara depot.

Obaidul Quader joined the program virtually from his official residence.

He said the progress of the construction work from Uttara to the Agargaon section scheduled to be completed in the first phase is 84.9 percent.

He further said that the progress of the construction work from Agargaon to Motijheel section scheduled to be implemented in the second phase is 59.7 percent and the overall progress of procurement of electrical and mechanical system, rolling stock and depot equipment is 54.4 percent.

Subscribe Shampratik Deshkal Youtube Channel

Comments

Shampratik Deshkal Epaper

Logo

Address: 10/22 Iqbal Road, Block A, Mohammadpur, Dhaka-1207

© 2024 Shampratik Deshkal All Rights Reserved. Design & Developed By Root Soft Bangladesh