Desk Report
Publish: 06 Apr 2022, 01:22 pm
Prime Minister Sheikh Hasina || Photo: Collected
Prime Minister
Sheikh Hasina has said that the Padma Bridge will be opened for traffic by the end
of this year. Work is in full swing to make the Padma Bridge open for vehicles
movement by the end of 2022.
The Prime Minister
made the remarks in response to a question from the Shahiduzzaman government of the Naogaon-2 constituency during the question and answer session of the Jatiya
Sangsad on Wednesday (April 7). Speaker Shirin Sharmin Chowdhury presided over
the question and answer session of the Prime Minister.
Earlier, Road
Transport and Bridges Minister Obaidul Quader had said that the Padma
Multipurpose Bridge could be opened to everyone for movement in June this year.
The Prime Minister
said the work on the approach road and service area at both ends of the Padma
Bridge project has been completed. The physical progress of the main bridge is
96.50 percent. Construction of carpeting, viaduct carpeting, and waterproof
membrane, movement joint of main bridge and viaduct, lamppost, aluminum railing,
gas pipeline, 400 kVA power, and railway line is in progress at present.
She said the Padma
Bridge is going to be one of the biggest challenging projects in the history of
a developing country like Bangladesh, overcoming all obstacles as part of the
bold move of the present government.
She also told the
parliament that the revised cost for the construction of the 6.15 km long
bridge has increased to Tk 30,193.39 crore.